Chelsea, Maine

Chelsea, Maine

View Interactive Map | Download Map PDF

The scope of work as a part of the Maine Power Reliability Program in Chelsea consists of the construction of a new 345 kV transmission line and the rebuilding of existing 115 kV and 34.5 kV transmission lines.

The new 345 kV transmission line (Section 3025) will run approximately 5.9 miles of from the Kennebec River to the Whitefield town line on the southern side of the corridor on H-frame wooden structures approximately 75 feet in height. Where the transmission line crosses the Kennebec River, one steel single pole approximately 132 feet above ground will be installed.

The rebuilding of approximately 5.9 miles of existing 115 kV transmission line (Section 60) will involve removing the existing line and constructing a new one in its place. Most of the rebuilt line will be relocated to the northwest side of the corridor and will be primarily constructed using 77 wooden single pole structures that are typically 75 feet in height. Where the transmission line crosses the Kennebec River, one steel single pole structure approximately 87 feet in height will be installed.

The existing 34.5 kV transmission line at the Kennebec River crossing will be rebuilt using two steel single pole structures that are approximately 87 feet in height.

The existing 115 kV transmission line near Augusta (Section 88) will be rebuilt using three wooden single pole structures approximately 75 feet in height.

Permits & Approvals

Chelsea Permit Approval

11/10/2009

Approval of permit by planning board
Download PDF (473.389 KB)


Chelsea Permit Application

10/26/2009

Application submitted to town for necessary permits
Download PDF


News & Events

Portland Press Herald reports on MPRP Milestone!

May 16, 2012

The delivery of the Larrabee Road Substation Autotransformer
Read More


Delivery of Larrabee Road Substation Autotransformer Saturday, May 19

May 12, 2012

Attention travelers! Possible delays on Route 202 between Greene and Lewiston
Read More


Bangor Daily News reports on the progress of the MPRP

May 02, 2012

CMP’s $1.4 billion upgrade project on schedule and budget
Read More


Kennebec River Crossing Construction Activities

December 16, 2011

Construction is ongoing on both sides of Brown’s Island
Read More


Brown's Island Towers have been constructed

December 06, 2011

Crews are stringing wire in Chelsea and Farmingdale
Read More


Transmission line work continues in Windsor, Chelsea, and Farmingdale

October 19, 2011

Crews continue to string conductor from Chelsea to Windsor
Read More


Line Rebuild near completion from Windsor to Chelsea

September 29, 2011

Rebuild of existing 115 kV line nearly complete in Windsor, Whitefield, Augusta, Chelsea
Read More


Transmission line rebuild nearing completion from Windsor to Chelsea

September 14, 2011

Transmission line rebuild nears completion as work continues by River Rd and Hankerson Rd in Chelsea
Read More


Possible Delays on Maine Ave. and Rail Trail, Farmingdale

September 1, 2011

Construction of new steel lattice towers at Browns Island Crossing may cause delays in weeks of Aug. 23 and 29
Read More


Crew Saves Detroit Barn

August 10, 2011

Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More


Albion Road Autotransformer Delivered

August 11, 2011

Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More


Section 60 reconstruction continues

July, 18 2011

The reconstruction of Section 60 makes progress in Chelsea, Windsor
Read More


Transmission & Distribution World features MPRP!

July 15, 2011

"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More


CMP donates Mud Pond to Stanton Bird Club

July 15, 2011

241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More


CMP's Policies Manage Osprey Nests Responsibly

July 12, 2011

Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More


Rebuild of Section 60 and Section 88

July 11, 2011

Transmission line construction progresses in Windsor, Augusta and Chelsea
Read More


Section 60 Rebuild Progresses

July 5, 2011

Reconstruction of Section 60 in Windsor and Chelsea continues
Read More


Transmission Line Construction in Chelsea, Windsor and Augusta

June 13, 2011

Rebuild of existing lines in Chelsea and Augusta continues as Sec. 41 in Windsor removed.
Read More


Herald/Telegram Feature: CMP & Local Timber Mat Producers

June 10, 2011

Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More


Clearing continues, construction begins from Windsor to Monmouth

5-3-2011

Clearing operations continue from Chelsea to Monmouth and crews are completing clearing operations and construction transmission lines from Chelsea to Windsor
Read More


Clearing in Chelsea

4/13/2011

Crews have begun clearing capable vegetation from Route 17 to the Kennebec River.
Read More


Clearing in Chelsea

4/13/2011

Crews have begun clearing capable vegetation from Route 17 to the Kennebec River.
Read More


Clearing Windsor to Chelsea Continues

4/12/2011

Clearing in Windsor, Whitefiled, Augusta and Chelsea continues between Griffin Road and White' Junkyard on Goodwill Drive
Read More