Construction Info

View Interactive Map | Download Map PDF
The part of the program located in Appleton involves work in the
existing CMP corridor that extends approximately two miles through the
northern portion of town from Liberty, southeasterly through Appleton,
and into Searsmont. The project involves the construction of a new 115
kV transmission line that will be carried on 75-foot H-frame structures ranging from approximately 55 feet to 70 feet in
height, with an average height of 61 feet.
Approval of permits by planning board and/or CEO
Download PDF
Application submitted to town for necessary permits
Download PDF
Clearing continues in Appleton
Read More
Clearing to begin in Appleton and Washington before the end of December
Read More
Crews to survey corridor in Morrill, Searsmont, Montville, Appleton, Liberty, Washington and Somerville in preparation for clearing
Read More
Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More
Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More
"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More
241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More
Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More
Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More
Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.
* If your town's not here, then we're not there