Construction Info

View Interactive Map | Download Map PDF
The part of the program located in Dixfield involves the rebuilding of
an existing 115 kV transmission line and the construction of a new 115
kV transmission line in the existing corridor that extends through the
southeastern portion of town for approximately 2,000 feet from Peru
northeasterly through Dixfield and into Canton.
The new 115 kV transmission line will run on single-pole wood structures averaging 75 feet in height and will be located in the existing corridor. The existing 115 kV transmission line, which currently runs on approximately 45-foot tall H-frame structures in the center of the corridor, will be moved to the south side of the corridor and placed on single-pole structures that are typically 75 feet in height
Approval of permit by planning board
Download PDF (387.886 KB)
Application submitted to town for necessary permits
Download PDF
The delivery of the Larrabee Road Substation Autotransformer
Read More
Attention travelers! Possible delays on Route 202 between Greene and Lewiston
Read More
CMP’s $1.4 billion upgrade project on schedule and budget
Read More
Clearing in Canton from Ludden Lane to Canton Point Road
Read More
Clearing crews move west of Town Farm Road toward Canton Point Road
Read More
The helicopter is scheduled to start trimming corridors this weekend
Read More
Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More
Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More
The clearing phase is underway in Livermore Falls, Jay, Canton, Dixfield, Peru & Rumford
Read More
Transmission reconstruction of Section 203 underway, clearing is ongoing
Read More
"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More
241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More
Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More
Clearing in Jay and now moving into Canton, Dixfield,and Peru
Read More
Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More
Clearing to begin soon and continue through the summer
Read More
Crews are currently surveying and flagging the Section 229 corridor in Livermore Falls, Jay, Canton, Dixfield, Peru and Rumford. Clearing is expected to begin soon.
Read More