Construction Info

View Interactive Map | Download Map PDF
In Dixmont, the project involves upgrades in approximately 6.5 miles of CMP transmission line corridor that runs through the town from Troy southeasterly to Monroe. These upgrades include the construction of a new 345 kV transmission line and the rebuilding of the existing 115 kV transmission line.
The existing 115 kV transmission line, which is
currently on the south side of the corridor and runs on H-frame
structures which are typically 45 feet above ground, will be removed.
It will be rebuilt on the north side of the corridor on monopole
structures approximately 75 feet in height.
The new 345 kV transmission line will run on H-frame structures approximately 75 feet in height.
Approval of permit by planning board
Download PDF
Application submitted to town for necessary permits
Download PDF
Approval of permit by planning board
Download PDF (87.5146 KB)
The delivery of the Larrabee Road Substation Autotransformer
Read More
Removal of the 115 kV is nearing completion
Read More
Attention travelers! Possible delays on Route 202 between Greene and Lewiston
Read More
CMP’s $1.4 billion upgrade project on schedule and budget
Read More
Crews prepare for construction of new 345 kV line
Read More
Crews remove the existing 115 kV line
Read More
Work is ongoing rebuilding a 115 kV line
Read More
Construction in Dixmont west of Garland Road
Read More
Transmission line work boarders the municipalities of Dixmont and Troy
Read More
Transmission line construction moves into Troy as prep work starts in Dixmont. Poles installed in Detroit & Plymouth, waiting for line to be strung.
Read More
Info Panel donated for the Dixmont Town House
Read More
Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More
The completion of clearing in some areas leads to new phase of construction
Read More
Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More
Clearing in Orrington has begun as of July, 25th
Read More
"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More
241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More
Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More
Clearing in Dixmont, Plymouth, Monroe and Frankfort
Read More
Clearing operations continue in Monroe and Frankfort and crews are laying mats along Section 203 for construction
Read More
Clearing operations continue in from Detroit to Frankfort in preparation for transmission line construction.
Read More
Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More
Clearing crews working from Detroit to Dixmont, starting in Monroe soon, followed by Winterport and Frankfort
Read More
Clearing crews are on schedule to complete clearing in sensitive resource areas in Pittsfield, Detroit, Plymouth, Troy, Dixmont, Monroe, Winterport and Frankfort this week.
Read More
Crews are clearing vegetation from Moosehead Trail/ Rt. 7 northwest towards Troy.
Read More
Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.
* If your town's not here, then we're not there