Construction Info

View Interactive Map | Download Map PDF
The part of the program located in the Town of Farmingdale involves work in an existing corridor that traverses the south-central portion of the town. In this corridor, which extends for approximately 4.2 miles from Browns Island on the Kennebec River to the West Gardiner town line, the project involves:
Approval of permit by planning board
Download PDF
Includes permit conditions set by Planning Board
Download PDF (26.9629 KB)
Application submitted to town for necessary permits
Download PDF (1.78 MB)
Crews working in the vicinity of Blaine Road in Farmingdale
Read More
Construction is ongoing on both sides of Brown’s Island
Read More
Crews are stringing wire in Chelsea and Farmingdale
Read More
Crews continue to string conductor from Chelsea to Windsor
Read More
Crews to start work near Fairway Lane, Ryder Road
Read More
Transmission line rebuild nears completion as work continues by River Rd and Hankerson Rd in Chelsea
Read More
Laying down mats for construction access in Farmingdale and West Gardiner.
Read More
Construction of new steel lattice towers at Browns Island Crossing may cause delays in weeks of Aug. 23 and 29
Read More
Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More
Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More
"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More
241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More
Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More
Crews continue clearing new corridor from W. Gardiner to Monmouth and the removal of Section 41 from W. Gardiner to Litchfield
Read More
Vegetative clearing progresses in the Section 60 corridor
Read More
Pole locations for the Section 60 rebuild in Farmingdale are being marked from Bowman Street Substation to the Kennebec River
Read More
Clearing progresses near Town House Rd in West Gardiner and Litchfield and continues wrapping up in the Section 60 corridor from Farmingdale to the Monmouth Substation.
Read More
Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More
Clearing operations continue from Chelsea to Monmouth and crews are completing clearing operations and construction transmission lines from Chelsea to Windsor
Read More
Clearing operations continue throughout the Section 212 corridor through Farmingdale, West Gardiner, Litchfield and Monmouth
Read More
Crews are beginning the decommissioning of Section 41, starting from South Monmouth Road to Bowman Substation
Read More
Crews are clearing from Northern Ave. to I-95
Read More
Clearing is occurring in the vicinity of Blane Road and I-95; clearing mostly complete near golf course
Read More
Crews are clearing near sensitive natural resources between the Kennebec River in Farmingdale and the Monmouth Substation before spring arrives.
Read More
Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.
* If your town's not here, then we're not there