Frankfort, Maine

Frankfort, Maine

View Interactive Map | Download Map PDF

In Frankfort, MPRP activities will be taking place in two corridors in the northern portion of town. One corridor, which currently houses an existing 115 kV line, runs west to east from the western Monroe Town Line to Marsh Stream and crosses following roads in Frankfort: East Main Street, Fisher Road and Marsh Stream Road. The second corridor, which currently houses an existing 345 kV line, runs north to south from the Winterport Town Line to the southern Monroe Town Line near Swanville (hereafter referred to as the Monroe-Swanville line) and crosses the following roads in Frankfort: Hamm Road, Loggin Road, Parker Lane, and Town Hill Road.

As part of the Maine Power Reliability Program, CMP proposes to construct two new transmission lines and rebuild two existing transmission lines in Frankfort:

Permits & Approvals

Frankfort Permit Approval

05/11/2010

Approval of permit by planning board
Download PDF (136.121 KB)


Frankfort Permit Application

08/03/2009

Application submitted to town for necessary permits
Download PDF


News & Events

Portland Press Herald reports on MPRP Milestone!

May 16, 2012

The delivery of the Larrabee Road Substation Autotransformer
Read More


Removal of the 115 kV line in Dixmont, Monroe and Frankfort

May 12, 2012

Removal of the 115 kV will continue into July
Read More


Construction in Orrington, Winterport and Frankfort

May 12, 2012

Crews prepare for construction of rebuilt 345kV transmission line
Read More


Delivery of Larrabee Road Substation Autotransformer Saturday, May 19

May 12, 2012

Attention travelers! Possible delays on Route 202 between Greene and Lewiston
Read More


Bangor Daily News reports on the progress of the MPRP

May 02, 2012

CMP’s $1.4 billion upgrade project on schedule and budget
Read More


Rebuild of a 345 kV line in Frankfort

March 05, 2012

Pre-construction actives begin in Frankfort
Read More


Tree trimming in Frankfort

January 16, 2012

Tree trimming ongoing from January into February
Read More


Transmission line work in Frankfort

January 16, 2012

Work is ongoing rebuilding a 115 kV line
Read More


Pre-construction activities in Frankfort

December 19, 2011

Construction crews prepare for Transmission Line operations in Frankfort
Read More


Clearing is progressing from Frankfort to Brooks

September 13, 2011

Clearing in Frankfort, Winterport, Monroe, Swanville and Brooks. Surveying complete in Waldo.
Read More


Clearing wraps up in Frankfort and moves toward Swanville this week

August, 24 2011

Clearing crews finish clearing on West Hill Road to Marsh Stream, and off Hamm Road in Frankfort
Read More


Crew Saves Detroit Barn

August 10, 2011

Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More


Clearing nears completion construction makes progress in northern towns

August, 15 2011

The completion of clearing in some areas leads to new phase of construction
Read More


Surveying underway in Frankfort, Monroe, Brooks and Waldo

August, 15 2011

Survey of right of way clearing limits is underway in Frankfort, Monroe, Brooks and Waldo
Read More


Albion Road Autotransformer Delivered

August 11, 2011

Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More


Clearing in Orrington has begun as of July, 25th

July, 28 2011

Clearing in Orrington has begun as of July, 25th
Read More


Transmission construction and clearing updates for Section 203

July, 18 2011

Transmission reconstruction of Section 203 underway, clearing is ongoing
Read More


Transmission & Distribution World features MPRP!

July 15, 2011

"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More


CMP donates Mud Pond to Stanton Bird Club

July 15, 2011

241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More


CMP's Policies Manage Osprey Nests Responsibly

July 12, 2011

Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More


Surveying in Orrington, Clearing Frankfort and Winterport

July 11, 2011

Crews currently surveying corridor and clearing will begin shortly
Read More


Clearing and Construction along Section 203

July 11, 2011

Clearing in Dixmont, Plymouth, Monroe and Frankfort
Read More


Clearing in Frankfort and Winterport

July 5, 2011

Crews are clearing the Section 388 corridor in Frankfort and Winterport and surveying in Orrington.
Read More


Clearing and Construction Prep from Pittsfield to Frankfort

July 1, 2011

Clearing operations continue in Monroe and Frankfort and crews are laying mats along Section 203 for construction
Read More


Clearing and construction from Frankfort to Orrington starting soon

June 16, 2011

Corridor Clearing and construction of Penobscot River crossing structures starting in next few weeks
Read More


Clearing progress in Section 203 corridor from Pittsfield to Frankfort

June 13, 2011

Clearing operations continue in from Detroit to Frankfort in preparation for transmission line construction.
Read More


Clearing beginning from Orrington to Frankfort

June 13, 2011

Clearing of the Section 388 corridor from Orrington Substation to the Section 203 juncture in Frankfort has begun in Orrington.
Read More


Herald/Telegram Feature: CMP & Local Timber Mat Producers

June 10, 2011

Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More


Surveying from Frankfort to Orrington

5-2-2011

Crews are surveying in Frankfort, Winterport, Bucksport and Orrington in preparation for clearing.
Read More


Clearing Continues from Detroit to Frankfort

5-2-2011

Clearing crews working from Detroit to Dixmont, starting in Monroe soon, followed by Winterport and Frankfort
Read More


Clearing from Pittsfield to Frankfort Progressing

4/13/2011

Clearing crews are on schedule to complete clearing in sensitive resource areas in Pittsfield, Detroit, Plymouth, Troy, Dixmont, Monroe, Winterport and Frankfort this week.
Read More


Surveying in Frankfort

4/12/2011

Crews are surveying the corridors in Frankfort in preparation for clearing operations.
Read More