In Leeds, the MPRP proposes to add a new 115 kV transmission line in the existing corridor that traverses the town from north to south in the western portion of town. The new 115 kV transmission line will run on single-pole structures averaging 75 feet in height adjacent to the existing lines for approximately 8.5 miles.

Permits & Approvals

Leeds Permit Approval

12/21/2009

Approval of permit by planning board and/or CEO
Download PDF


Leeds Permit Application

11/16/2009

Application submitted to town for necessary permits
Download PDF


News & Events

MPRP reaches milestone with 1000th pole set in Leeds

January 05, 2012

CMP transmission project marks milestone as crews set 1000th pole
Read More


Construction continues in Leeds

December 28, 2011

Crews work on new 115 kV line
Read More


Construction Preparation in Leeds

September 29, 2011

Crews are beginning to stockpile timber mats on CMP's corridor in Leeds
Read More


Crew Saves Detroit Barn

August 10, 2011

Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More


Albion Road Autotransformer Delivered

August 11, 2011

Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More


Transmission & Distribution World features MPRP!

July 15, 2011

"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More


CMP donates Mud Pond to Stanton Bird Club

July 15, 2011

241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More


CMP's Policies Manage Osprey Nests Responsibly

July 12, 2011

Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More


Prep for New Section 251 in Livermore Falls

July 11, 2011

Crews prepare for new transmission line construction in the Section 200 corridor
Read More


Herald/Telegram Feature: CMP & Local Timber Mat Producers

June 10, 2011

Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More


What's HappeningIn Your Town

Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.

* If your town's not here, then we're not there