The project in Morrill involves construction of a new 115 kV transmission line, Section 254, within the existing corridor, which now includes a 345 kV electrical transmission line. The proposed new transmission line will be located parallel to and northwest of the existing 345 kV line and run on H-Frame structures ranging from approximately 55 feet to 70 feet in height, with an average height of 61 feet.

Permits & Approvals

Morrill Permit Amendment Approval

07/06/2010

Approval of amendment to original permit application
Download PDF


Morrill Permit Amendment Application

06/25/2010

Application for amendment to original permit application
Download PDF


Morrill Permit Approval

08/07/2009

Approval of permit by planning board and/or CEO
Download PDF


Morrill Permit Application

05/22/2009

Application submitted to town for necessary permits
Download PDF


News & Events

Clearing operations in Morrill

January 16, 2012

Clearing continues in Morrill
Read More


Clearing has begun in Morrill

October 12, 2011

Clearing reaches from Morrill into Waldo
Read More


Surveying from Morrill to Windsor

September 14, 2011

Crews to survey corridor in Morrill, Searsmont, Montville, Appleton, Liberty, Washington and Somerville in preparation for clearing
Read More


Crew Saves Detroit Barn

August 10, 2011

Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More


Albion Road Autotransformer Delivered

August 11, 2011

Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More


Transmission & Distribution World features MPRP!

July 15, 2011

"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More


CMP donates Mud Pond to Stanton Bird Club

July 15, 2011

241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More


CMP's Policies Manage Osprey Nests Responsibly

July 12, 2011

Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More


Herald/Telegram Feature: CMP & Local Timber Mat Producers

June 10, 2011

Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More


What's HappeningIn Your Town

Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.

* If your town's not here, then we're not there