Construction Info

View Interactive Map | Download Map PDF
The portion of the MPRP located in Pownal involves the construction of two new 345 kV transmission lines, the realignment and rebuild of portions of existing 345 kV and 115 kV transmission lines, and the expansion of the existing Surowiec Substation.
Surowiec Substation Expansion
The MPRP proposes to expand the 345 kV portion of the Surowiec Substation to accommodate two new 345 kV transmission lines. The proposed modifications to the substation include: (1) the rebuild of the existing 345 kV bus on the north side of the substation to accommodate the new 345 kV lines; and (2) the addition of one new 115 kV breaker to the existing 115 kV bus on the south side of the substation to improve system operation. Switches and other minor equipment will also be added to the substation.
New 345 kV Transmission Lines
CMP proposes to construct two new 345 kV transmission lines (Section 3020 and Section 3026) that will interconnect with the Surowiec Substation in Pownal. Section 3020 will extend south from the Surowiec Substation to North Yarmouth while Section 3026 will extend north from the substation to Durham.
The new Section 3020 transmission line will be constructed approximately 95 feet to the east of the existing 345 kV line. To accomplish this, the two existing 115 kV lines will be relocated farther to the east within the corridor. The new 345 kV line will be constructed on H-frame structures approximately 75 feet in height, while the two 115 kV lines will be rebuilt using single pole structures approximately 75 feet in height.
The new Section 3026 transmission line will be constructed in the space between the existing 115 kV transmission line and the gas pipeline on H-frame structures that have a typical height of approximately 75 feet.
Rebuild Existing 345 kV and 115 kV Transmission Lines
To accommodate the routing of the two new 345 kV transmission lines into the Surowiec Substation, a number of existing 345 kV and 115 kV transmission lines connecting at the substation must be realigned and rebuilt typically using H-frame structures approximately 45 feet in height or single-pole structures approximately 75 feet in height. Some lines may need to be temporarily rerouted until the substation expansion is completed, after which the temporary lines will be removed.
Special Exception to residential noise ordinance for construction of Surowiec Substation
Download PDF
Approval of permit by planning board and/or CEO
Download PDF
Supplemental information requested by Planning Board
Download PDF
Supplemental information requested by Planning Board
Download PDF
Supplemental information requested by Planning Board
Download PDF
Application for special request to noice ordinance for construction of Surowiec Substation
Download PDF
Supplemental information requested by Planning Board
Download PDF
Application submitted to town for necessary permits
Download PDF
Expansion of Surowiec Substation requires a series of modifications
Read More
Construction rebuilds in Pownal nears competition as crews perform restoration work
Read More
Clearing crews removing mats after completing clearing
Read More
Transmission line work is ongoing in Pownal between Fickett Road and the North Yarmouth Town Line
Read More
Construction crews begin to string line on Allen Road
Read More
Transmission line construction is at various phases in Pownal
Read More
Clearing crews move from Pownal to Durham and Auburn
Read More
Clearing operations continue toward Durham and the transmission line rebuild is near complete to N. Yarmouth
Read More
Crews in Pownal continue installing a new transmission line
Read More
Clearing ongoing at Pond Rd in Lewiston. A second crew with start next week at Fickett Rd in Pownal and work toward Durham.
Read More
Construction crews prepare mat installation near Surowiec Substation
Read More
Work is scheduled from Surowiec Substation south towards Sweetser Road and Elmwood Road
Read More
Clearing operations in North Yarmouth continue south of Lufkin Road towards Gray Road
Read More
Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More
Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More
Clearing & Mowing underway in North Yarmouth
Read More
Local fire departments in Troy, Pownal, Canton and Somerville each received a new AED from the MPRP
Read More
Pownal: clearing completed to N. Yarmouth, construction continues
Read More
Prep for construction is underway in Pownal as clearing is nearing completion from Surowiec to North Yarmouth
Read More
"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More
241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More
Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More
Clearing operations south of Surowiec Substation wrapping up as Section 167 rebuild construction ramps up
Read More
Crews preparing corridor for transmission line construction in the Section 166/167 corridor
Read More
North & South of Suroweic Substation to be cleared of capable vegetation in the near future.
Read More
Corridor from new Larrabee Rd Substation to Suroweic Substation to be cleared soon
Read More
Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More
corridor clearing to begin within the next few weeks
Read More
Crews are surveying north of Surwiec Substation for upcoming clearing activities.
Read More