The project in Wells will take place entirely within the existing transmission line corridor which runs from Kennebunk to North Berwick in the western portion of town for approximately 7.3 miles. The project involves the installation of a new 345 kV transmission line, Section 3022, on the eastern side of the corridor on wooden H-frame structures averaging 75 feet in height.

Permits & Approvals

Wells Permit Approval

05/18/2011

Findings of Facts and Notice of Decision approving the permit for work in Wells
Download PDF (386.624 KB)


Wells Permit Application

11/01/2010

Permit application for work in Wells
Download PDF (407.021 KB)


News & Events

Maine Power Reliability Program featured on Seacoast Online

January 19, 2012

CMP crews working on power line upgrade
Read More


Clearing operation progress in Wells

January 16, 2012

Clearing crew in Wells mobilize to Perry Oliver Road and Route 9
Read More


Clearing operations underway in Wells

December 28, 2011

Clearing north of Bill’s Lane and Bald Hill Road
Read More


Pre-clearing activities in Wells

December 19, 2011

The clearing contractor is completing the pre-clearing operations in Wells
Read More


Surveying Segment 27

4/12/2011

Crews are surveying the corridor in North Berwick, South Berwick and Wells for clearing.
Read More


What's HappeningIn Your Town

Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.

* If your town's not here, then we're not there