Construction Info

View Interactive Map | Download Map PDF
The part of the program located in the Town of Windsor involves the construction of a new substation (Coopers Mills Road), the decommissioning of the existing substation (Maxcys) and work in three transmission line corridors that traverse the Town.
Decommissioning of Maxcy’s Substation
Maxcy’s Substation is a major hub of the existing transmission grid, providing 115 kV service to most of CMP’s northern service territory. The substation will be decommissioned and replaced with a new substation (see below). The area will become part of an existing right-of-way where three transmission corridors converge.
Construction of Coopers Mills Road Substation
A new substation will be located in an area just west of Coopers Mills Road. A 2,700 foot permanent gravel access road will be constructed on the north side of Maxcy’s Mill Road. The total area of the site, including substation yard and access road, will be approximately 30 acres. A new 170-foot microwave tower will be installed at the substation for communications purposes during outages.
The substation will be surrounded by chain link fencing. There will be a control house and a holding tank within the substation yard, and lighting along the perimeter fence, above the control house door, and within the yard.
Transmission Line Corridors
Construction within an approximate 13.6 miles of transmission line corridors will include the following:
West of Coopers Mills Road Substation: The project in this area will include the installation of a new 345 kV line (Section 3025), which will be primarily constructed on 2-pole wooden H-frame structures approximately 75 feet in height; and the rebuilding of two existing 115 kV lines (Sections 60 and 88), which will be primarily constructed on single wooden poles approximately 75 feet in height
North of Coopers Mills Road Substation: The project in this area will include the installation of a new 345 kV line (Section 3024), which will be primarily constructed on 2-pole wooden H-frame structures approximately 75 feet in height, and the rebuild of two existing 115 kV transmission lines on single pole structures averaging 75 feet in height.
East of Coopers Mills Road Substation: The project in this area will include the installation of a new 115 kV line (Section 254), which will be primarily constructed on 2-pole wooden H-frame structures
Renewal of floodplain management permit
Download PDF
Approval of permit by planning board and/or CEO
Download PDF
Application submitted to town for necessary permits
Download PDF
Approval of amendment to original shoreland zoning permit application
Download PDF
Amendment to original permit application
Download PDF
Approval of permit by planning board and/or CEO
Download PDF
Application submitted to town for necessary permits
Download PDF
Signed Permit for rainwater drainage tank at Coopers Mills Substation
Download PDF
Clearing continues in Windsor
Read More
Occasional blasting will be occurring though December 2011 and January 2012
Read More
Clearing activities continue in China & Windsor
Read More
Crews continue to string conductor from Chelsea to Windsor
Read More
Rebuild of existing 115 kV line nearly complete in Windsor, Whitefield, Augusta, Chelsea
Read More
Transmission line rebuild nears completion as work continues by River Rd and Hankerson Rd in Chelsea
Read More
Transmission line construction is on going in the vicinity of Griffin Road
Read More
Crews are surveying and flagging the Section 67 corridor from Windsor to Benton
Read More
Coopers Mills Substation site development has begun
Read More
The reconstruction of Section 60 makes progress in Chelsea, Windsor
Read More
Site Development for the new Coopers Mills Substation scheduled to begin next month
Read More
Transmission line construction progresses in Windsor, Augusta and Chelsea
Read More
Reconstruction of Section 60 in Windsor and Chelsea continues
Read More
Rebuild of existing lines in Chelsea and Augusta continues as Sec. 41 in Windsor removed.
Read More
Clearing operations continue from Chelsea to Monmouth and crews are completing clearing operations and construction transmission lines from Chelsea to Windsor
Read More
Clearing in Windsor, Whitefiled, Augusta and Chelsea continues between Griffin Road and White' Junkyard on Goodwill Drive
Read More
Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.
* If your town's not here, then we're not there