Woolwich, Maine

Woolwich, Maine

View Interactive Map | Download Map PDF

The project in Woolwich will involve separating two existing 345 kV transmission lines located on the northerly towers between the Kennebec River Crossing and Chopps Point Road. Similar work will be undertaken on the Bowdoinham side of the river. In order to accommodate the separation of the lines, the southerly tower on the river will be upgraded to a size and height similar to the northerly tower (approximately 330 feet in height) ; the southerly tower located uphill from the river near Chopps Point Road will be replaced with a monopole. Once completed, the northerly towers will carry a single 345 kV transmission line and the southerly towers will carry the existing 115 kV line and the relocated 345 kV line. The project will also involve modifications to two other structures near Chopps Point Road.

Local permitting efforts will begin one year prior to expected construction start date per request of the Planning Board.

What's HappeningIn Your Town

Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.

* If your town's not here, then we're not there