Maine Power

Construction Info


Detroit, Maine

Detroit, Maine

View Interactive Map | Download Map PDF

In Detroit, the project involves work in an existing 218 foot wide transmission line corridor containing Sections 203, 66, and 67 that traverses the central portion of the town. In this corridor, which extends for approximately 6.9 miles from the Pittsfield to Plymouth town lines, the project involves:

Permits & Approvals

Detroit Shoreland Zoning Permit Approval

08/31/2010

Approval of permit by planning board
Download PDF


Detroit Flood Hazard Permit Approval

08/31/2010

Approval of permit by planning board and/or CEO
Download PDF


Detroit Permit Approval

01/14/2010

Approval of permit by planning board
Download PDF


Detroit Supplemental Information

10/01/2009

Supplemental information requested by Planning Board
Download PDF


Detroit Shoreland Zoning Permit Application

08/07/2009

Application submitted to town for necessary permits
Download PDF


Detroit Flood Hazard Permit Application

08/07/2009

Application submitted to town for necessary permits
Download PDF


News & Events

Portland Press Herald reports on MPRP Milestone!

May 16, 2012

The delivery of the Larrabee Road Substation Autotransformer
Read More


Update to the removal of the 115 kV line in Detroit, Troy and Dixmont

May 12, 2012

Removal of the 115 kV is nearing completion
Read More


Delivery of Larrabee Road Substation Autotransformer Saturday, May 19

May 12, 2012

Attention travelers! Possible delays on Route 202 between Greene and Lewiston
Read More


Bangor Daily News reports on the progress of the MPRP

May 02, 2012

CMP’s $1.4 billion upgrade project on schedule and budget
Read More


Construction of 345 kV line in Detroit

April 18, 2012

Construction is ongoing in Detroit
Read More


Pre-construction activities in Detroit are ongoing

March 19, 2012

Construction crews continue to install timber mats
Read More


Construction continues in Detroit, Troy and Dixmont

March 05, 2012

Crews remove the existing 115 kV line
Read More


Construction of the new 345 kV line in Detroit

March 05, 2012

Pre-construction activities are underway in Detroit
Read More


Poles set in Detroit, Plymouth - Work starting in Troy, Dixmont

September 14, 2011

Transmission line construction moves into Troy as prep work starts in Dixmont. Poles installed in Detroit & Plymouth, waiting for line to be strung.
Read More


Line rebuild complete from Detroit/Pittsfield to Mutton Lane in Clinton

September 09, 2011

Crews completed rebuilding the existing 115-kV line from Detroit SS to Mutton Lane in Clinton, continue southward.
Read More


Crew Saves Detroit Barn

August 10, 2011

Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More


Construction continues in Detroit

August, 15 2011

Crews focus on rebuilding 115kv lines and the installation of 345kv lines in Detroit
Read More


Albion Road Autotransformer Delivered

August 11, 2011

Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More


Line construction is completed in Pittsfield

July, 28 2011

Line construction is completed in Pittsfield
Read More


Transmission construction and clearing updates for Sections 66 and 67

July, 18 2011

Transmission reconstruction of Sections 66 to 67 underway, more work starting soon
Read More


Transmission construction and clearing updates for Section 203

July, 18 2011

Transmission reconstruction of Section 203 underway, clearing is ongoing
Read More


Transmission & Distribution World features MPRP!

July 15, 2011

"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More


CMP donates Mud Pond to Stanton Bird Club

July 15, 2011

241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More


CMP's Policies Manage Osprey Nests Responsibly

July 12, 2011

Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More


Clearing and Construction along Section 203

July 11, 2011

Clearing in Dixmont, Plymouth, Monroe and Frankfort
Read More


Clearing and Construction Prep from Pittsfield to Frankfort

July 1, 2011

Clearing operations continue in Monroe and Frankfort and crews are laying mats along Section 203 for construction
Read More


Clearing progress in Section 203 corridor from Pittsfield to Frankfort

June 13, 2011

Clearing operations continue in from Detroit to Frankfort in preparation for transmission line construction.
Read More


Transmission Line Construction in Pittsfield

June 13, 2011

The rebuilding of Section 67 continues as crews prepare the corridors for the installation of a new line.
Read More


Herald/Telegram Feature: CMP & Local Timber Mat Producers

June 10, 2011

Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More


Clearing Continues from Detroit to Frankfort

5-2-2011

Clearing crews working from Detroit to Dixmont, starting in Monroe soon, followed by Winterport and Frankfort
Read More


Clearing from Pittsfield to Frankfort Progressing

4/13/2011

Clearing crews are on schedule to complete clearing in sensitive resource areas in Pittsfield, Detroit, Plymouth, Troy, Dixmont, Monroe, Winterport and Frankfort this week.
Read More


Detroit Clearing

3/31/2011

Crews are clearing vegetation in the vicinity of Troy Road working northwest and southeast down the corridor.
Read More