North Berwick, Maine

North Berwick, Maine

View Interactive Map | Download Map PDF

The project proposed in North Berwick will take place within the existing transmission line corridors that traverse the town line from Wells to South Berwick in the southern portion of town for approximately 2.7 miles. The project involves the installing a new 345 kV transmission line, Section 3022, on the eastern side of the corridor on wooden H-frame structures averaging 75 feet in height, as well as the rebuilding of the existing 115 kV transmission line Section 250 on single pole structures averaging 75 feet in height. Section 250 is proposed to leave its existing corridor and be rebuilt in the Section 140 corridor to the Goulds Bridge Road Substation, where it will follow Section 197 back to the existing Section 250 corridor.

Permits & Approvals

North Berwick Permit Approval

03/10/2011

Planning Board approval for MPRP work in North Berwick.
Download PDF (23.1211 KB)


North Berwick Permit Application

01/04/2011

Permit application for work in North Berwick
Download PDF (1016.58 KB)


News & Events

Portland Press Herald reports on MPRP Milestone!

May 16, 2012

The delivery of the Larrabee Road Substation Autotransformer
Read More


Delivery of Larrabee Road Substation Autotransformer Saturday, May 19

May 12, 2012

Attention travelers! Possible delays on Route 202 between Greene and Lewiston
Read More


Bangor Daily News reports on the progress of the MPRP

May 02, 2012

CMP’s $1.4 billion upgrade project on schedule and budget
Read More


Vegetative Clearing in North Berwick

January 16, 2012

Clearing operations have commenced in North Berwick
Read More


Crew Saves Detroit Barn

August 10, 2011

Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More


Albion Road Autotransformer Delivered

August 11, 2011

Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More


Clearing in South Berwick has completed mowing operations

July, 28 2011

Clearing in South Berwick has completed mowing operations
Read More


Transmission & Distribution World features MPRP!

July 15, 2011

"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More


CMP donates Mud Pond to Stanton Bird Club

July 15, 2011

241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More


CMP's Policies Manage Osprey Nests Responsibly

July 12, 2011

Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More


Herald/Telegram Feature: CMP & Local Timber Mat Producers

June 10, 2011

Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More


Clearing to begin in North and South Berwick

July 2011

Clearing to begin in July
Read More


Surveying in North and South Berwick

5-2-2011

Crews are surveying in South Berwick and the eastern boundary of North Berwick in preparation for clearing.
Read More


Surveying Segment 27

4/12/2011

Crews are surveying the corridor in North Berwick, South Berwick and Wells for clearing.
Read More