The part of the MPRP located in Saco involves the construction of a new 345 kV transmission line and the rebuilding of a 115 kV transmission line and 34.5 kV transmission line within the existing CMP corridor.
The corridor extends approximately 6.75 miles from the municipal border of Saco/Scarborough to the existing Louden Substation and continues to the Saco River where it crosses into Biddeford. Structure heights will vary due to terrain and the need to achieve spans that will avoid or minimize impacts to natural resources.
The new 345 kV transmission line, Section 3021, will be installed roughly in the center of the existing corridor on H-frame structures approximately 75 feet in height. The existing 115 kV transmission line, Section 238, currently runs on H-frame structures approximately 45 feet in height, which will be removed and replaced with single-pole structures approximately 75 feet in height. A three-pole structure will be installed at the crossing of the Saco River.
The existing 34.5 kV transmission line, Section 175, currently runs on single-pole structures approximately 35 feet in height with the conductors arranged horizontally. These structures will be removed and replaced with single-pole structures approximately 45 feet in height with the conductors arranged vertically.
MPUC Order granting CMP exemption to the city zoning ordinance
Download PDF (57 KB)
Report from PUC Examiner regarding CMP's request for ordinance exemption
Download PDF (54.5 KB)
CMP's request for an exemption to the city ordinance requiring all high-voltage transmission lines be underground
Download PDF (75.5 KB)
Application submitted to city for MPRP
Download PDF (152.996 KB)
The delivery of the Larrabee Road Substation Autotransformer
Read More
Attention travelers! Possible delays on Route 202 between Greene and Lewiston
Read More
CMP’s $1.4 billion upgrade project on schedule and budget
Read More
Construction progresses from Saco into Biddeford
Read More
Construction activities are underway from Louden Road Substation to the Saco River
Read More
Clearing operations south of McKenney Road
Read More
Crews will be matting and cutting near Loudon Substation
Read More
Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More
Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More
"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More
241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More
Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More
Clearing phase underway in the Section 220 corridor in Saco
Read More
Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More
Corridor clearing to begin in Saco
Read More
Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.
* If your town's not here, then we're not there