The part of the program located in the Town of Stockton Springs involves work in an existing corridor that extends from the Prospect municipal boundary to the Searsport municipal boundary in the westerly part of town. The project involves rebuilding the existing 115 kV transmission line on single-pole structures typically 75 feet in height, which will be placed in the same general location as the existing 115 kV line.
Approval of permit by planning board and/or CEO
Download PDF
Approval of permit by planning board and/or CEO
Download PDF
Application submitted to town for necessary permits
Download PDF
Application submitted to town for necessary permits
Download PDF
Rebuild of 115 kV line is underway
Read More
Crews preparing construction access in Searsport, Stockton Springs, and Prospect
Read More
Clearing completed in Searsport, construction to commence in August
Read More
Rebuild of 115 kV line Section 86 starting within next month
Read More
Minor clearing and site preparation work for transmission line construction on existing Section 86
Read More