In Albion, the project will include the construction of a new 345 kV transmission line, rebuilding of two
115 kV transmission lines and the removal of the existing 115 kV
transmission line in the existing corridor that traverses the town from
the Albion-China municipal boundary in a northwesterly direction
towards the Albion-Winslow municipal boundary.
The new 345 kV transmission line will run on H-frame structures approximately 75 feet in height on the western side of the corridor. The existing 115 kV transmission line running on H-frame structures will be removed and the new 115 kV line will be constructed using single-pole structures approximately 75 feet in height.
Approval of permits by planning board and/or CEO
Download PDF
Application submitted to town for necessary permits
Download PDF
Anthony Iannello and Jared Haney, L.E. Myers Co., fought a barn fire on Troy Rd. in Detroit while returning from MPRP jobsite.
Read More
Photos of the massive 345-kV autotransformer being delivered to Benton from Searsport.
Read More
Crews are surveying and flagging the Section 67 corridor from Windsor to Benton
Read More
"Jobs Meet Reliability" - How the MPRP is Strengthening Maine's Grid and Economy
Read More
241 acres of land surrounding Mud Pond in Monmouth transferred for conservation
Read More
Hundreds of ospreys nest on our utility poles. We share your concerns for the safety of these birds, and our company has policies and personnel in place to manage these nests responsibly.
Read More
Portland Press Herald/ Maine Sunday Telegram article highlights work of local timber mat suppliers for the MPRP
Read More
Looking for project information about the Maine Power Reliability Program in your community? Select your town or city from the drop-down list to find construction updates, permits, maps and more.
* If your town's not here, then we're not there